Project Overview

Project Component: MNB-01 Bridge Construction

Location: Ramban–Banihal section, NH-44 (J&K)

Program: NHDP Phase-II

Mode: Engineering, Procurement & Construction (EPC)

Project Description

This project involved the construction of bridge foundations and substructure works (MNB-01 Bridge) as part of the four-laning of the Ramban–Banihal section of NH-44 (earlier NH-1A) in Jammu & Kashmir. The work was executed under the NHDP Phase-II program on an Engineering, Procurement & Construction (EPC) basis.


Scope of Work

Our comprehensive scope for the substructure works included:

  • Open foundation construction.
  • Deep excavation and dewatering operations.
  • RCC footings and pier construction.
  • Foundation works along with associated structural and civil works.
  • Strict compliance with approved technical specifications and safety norms.

Project Outcome

The project was completed satisfactorily within the agreed timeframe, demonstrating strong technical capability, precision workmanship, and evident expertise in executing complex bridge substructure works in challenging site conditions.